Emerson Process Management Website Home Emerson Process Management Emerson Corporate BusinessEmerson Corporate website Company OverviewEmerson Corporate BrandsEmerson Corporate Investor Relations  
SearchIndustry Centers
Solutions
Community
Video Central
Resources
Have Fun
Site Map
Reach Us Site Feedback

Success Stories

Chemical | Zeneca, Ltd.

In 1997, ZENECA chose a DeltaV digital automation system to control raw materials at the site of Saint Clair-du-Rhone, south of Lyon, France. The key challenge of the project was a very quick installation and commissioning timeframe.

ZENECA is a leading British-based international group in the bioscience sector, formed during the separation of the ICI Group in 1993. It comprises four divisions: Pharmaceuticals, Agrochemicals, Science, and Specialities.

Within Specialities, ZENECA Limited, at the site of Saint Clair-du-Rhone (France), is a production and development plant with approximately 300 chemical products in the fine organic chemicals field, mainly ranges of colorants for:

  • leather
  • paper and inks
  • inkjet printers and reprography additives in a fast-growing market

ZENECA is internationally oriented and exports 85 percent of its production; ZENECA is also innovative, with the introduction of technology such as the membrane liquefaction technique and adopting the environmental approach with colour removal/detoxification by electroflocculation. When modernizing its production facilities, ZENECA chose DeltaV to manage the bulk liquid raw materials, solvents, and utilities of one of its active ingredient synthesis units, which comprises 45 reactors between 1 and 75 m3, one third of which are greater than 25 m3.

The project consisted of replacing a raw materials management and distribution system that was no longer capable of meeting production requirements. The ultimate objective of the project was to attain a new target: 99.9 percent availability.

The project was under the direction of Louis Chanal, ZENECA¹s manager of the Electricity/Instrumentation department of the Maintenance operation.

Two solutions were considered:

  • a programmable, controller-based solution with one PLC per product (15), with overall supervision.
  • an integrated scalable system solution.

Two studies were launched to evaluate the two approaches. A key decision factor was the implementation time since ZENECA had only four weeks, corresponding to the annual shutdown of the site to install and commission one of the two approaches.

Another key decision factor that influenced ZENECA's investigation was that the standard chosen for supervision at St Clair-du-Rhône was FIX, from Intellution. The first solution meant having to program the 15 PLCs AND the supervision (mapping tables), which is quite engineering-intensive.

The second solution, the DeltaV system, proposed by Emerson Process Management, simplified ZENECA's task and saved time, because of its single object-oriented database, IEC 1131-3 standard, ISA 88, and drag-and-drop SFC development.

Since the production unit operates on a batch basis, this was the perfect solution. To find a compromise between 15 PLCs and one scalable system, ZENECA chose to distribute the tasks over five DeltaV controllers, all with redundancy, on two control PCs.

Since then, some key highlights recorded include:

  • procurement of all the hardware in record time
  • one week of training at Emerson Lyon (France) for three persons
  • assistance with on-site engineering for two weeks, provided by Emerson

In mid-July 1997, work began on wire-to-wire identification of the old system and in developing control strategies on the DeltaV system. On August 25th, the day of their return to work, the operators could use the new system.

André Garcia, from CEGELEC contractor, who had designed and programmed the entire application, was pleased to discover that he had structured DeltaV so well, because operator training was much easier than he had anticipated. The operators had no difficulty learning how to control their process using the DeltaV system or using the new-found information to improve plant performance. To date, the DeltaV system performance has been excellent.

In addition, a Platinum 24-hour-a-day contract has been concluded in order to comply with the 99.9 percent availability policy.

This co-operation has enabled real progress in quality control activities, operational tasks have been simplified, and the operators are seeing improved plant performance. Because of the success of this project, Mr. Chanal and the ZENECA organization are looking to scale up the DeltaV system to handle additional I/O.

back to top




     


Send comments to:
info@easydeltav.com

 



© 1996-2008 Emerson Process Management. All rights reserved.
Legal and Privacy Statements